    In November of 2014 voters passed a school bond for a total of $102,545,000. Of that $17,650,000 was allocated to district wide technology upgrades. Part of that included District-wide network infrastructure upgrades including wireless internet enhancements, district phone system replacement and network operations improvements. These improvements began to take place in June of 2015. 

    District Bond Website can be found here.

  • District Wide Network Upgrade Timelines

     

    Network assessment :                                      Summer 2014          Complete

    Network bid package released:                         January 2015           Complete

    Network bids received and Vendor Selected :     February 2015          Complete

    Vendor site walk and pre design meetings:        February 2015          Complete

    Po issued for network project:                          April 1, 2015            Complete

    Network replacement starts :                           June 9, 2015            Complete

    Network replacement completion:                     August 7, 2015        Complete