    In November of 2014 voters passed a school bond for a total of $102,545,000. Of that $17,650,000 was allocated to district wide technology upgrades. Within that 17 million dollars was the upgrade of the districts phone system . These needed upgrades will enhance staff communication as well as increase the safety and security of our students and staff. 

     District Bond Website can be found here.

    District Phone Upgrade Timelines

     

    Phone assessment :        Summer 2014    Complete

    Phone bid package released:       January 2015  Complete

    Phone bids received and Vendor Selected :       February 2015  Complete

    Vendor site walk and pre design meetings:       February 2015  Complete

    Po issued for phone project:       April 1, 2015  Completed

    Phone replacement starts :       June 9, 2015    Completed

    Phone replacement completion:       August 31, 2015 Completed