BOND 2023 PROJECT INFORMATION
It has been nearly 10 years since Duncanville ISD held its last bond election. All projects associated with Bond 2014 were completed by 2019, and the district saved approximately $3 million on bond projects.
The Citizen's Facility Advisory Committee, made up of two dozen citizens, community leaders, campus staff, and parents, met over the course of the summer to study and prioritize the district's needs and this bond proposal is based on their recommendations.
Proposition A |
Proposition B |
|
|
|
|
|
|
|
|
TOTAL FOR PROP A: $161,177,000 | TOTAL FOR PROP B: $8,823,000 |
Return to Bond Home Page
MAJOR PROJECTS
85% OF TOTAL BOND
Campus Reconfigurations
Interior architectural refresh (flooring, paint, ceilings, and wall finishes), major renovations, new HVAC units and lighting at the following schools to accommodate new grades for campus reconfiguration:
- Brandenburg Intermediate will become a 6-8 Choice MS
- Daniel Intermediate becomes a K-5 Elementary
- Hardin Intermediate becomes a K-5 Elementary
- Central Elementary becomes a K-8 Choice School
- Smith Elementary becomes an Early Childhood Academy
Career & Technical Education (CTE) Addition and Expansion at Duncanville High School
New CTE Wing could potentially provide dedicated space for:
|
|